A building permit is municipal authorization that allows you to begin renovation or construction work with full guarantees. In practice, a building permit can be granted from the day of registration (affidavit) to several months later (major work with reports). The actual time frame depends on the scope of the work, the documentation, and the local council.
What determines the duration of the building permit?
Three variables are key: the type of work, the quality of the application, and the administrative workload of the municipality. If your renovation is interior and does not affect the structure, the building permit is usually granted with prior notification or a responsible declaration; if it affects the façade, roof, structure, extensions, or change of use, you will need a building permit with a technical project and, therefore, more time. A complete file, with no inconsistencies between plans, reports, and measurements, cuts down on much of the paperwork.
Types of procedures and approximate processing times
There is no single deadline; each local council sets its own procedure. As a guide for planning purposes, this table summarizes the most common scenarios for housing building permits:
| Procedure | When does it apply? | Approximate start time |
|---|---|---|
| Affidavit / prior notification | Interior, without structure or facade | Immediately to 72 hours after registration (according to local regulations) |
| Minor works permit | Limited actions, without structure | 1–4 weeks, if there are no requirements |
| Major construction permit | Structure, facade/roof, extensions, change of use | 1–3 months; may be extended to 4–6 months with reports |
| Additional reports (heritage, environment) | Protected properties or BIC areas | +4–12 extra weeks |
| Occupation of public roads (scaffolding, containers) | If you occupy the sidewalk or roadway | 3–15 days, in parallel with the license |
These deadlines are approximate and must be confirmed with your local municipality. You can check the technical framework in the Technical Building Code and the legal basis in the LOE. For reference on the application process, see the Madrid City Council guide.
How to fit the building permit into your schedule
The key is to reach the milestone of "building permit granted" before signing non-refundable orders or booking critical trades. Divide your planning into three parallel tracks: technical documentation, licenses, and procurement. In comprehensive renovations, the licensing track usually marks the critical path, so orders for exterior carpentry, kitchens, or HVAC equipment will be confirmed when you have clear dates. In interior renovations by responsible declaration, you can synchronize the arrival of materials with greater agility.
What documents speed up (or slow down) the granting process?
A building permit is issued when the documentation is complete and consistent. For minor works or notifications, a report, simple plans, and measurements are sufficient; for major works, a technical project with plans, a report, specifications, and a budget are required, in addition to a health and safety study and the appointment of a project manager. If the report says one thing and the plans another, you will receive a request for further information and lose weeks. Also check that fees and waste bonds are correctly paid to avoid delays.
Signs that your work will take longer
If you plan to open holes in load-bearing walls, modify the façade, enclose a terrace, increase the usable area, or work on a protected building, expect a longer building permit process. Heritage reports and community authorizations add steps and validations. When the work affects common elements such as patios, shunts, downspouts, roofs, or structures, in addition to the municipal building permit, you will need formal neighborhood agreements; it is advisable to work on these in parallel so as not to delay the schedule.
Strategy to minimize downtime without taking risks
A good building permit strategy begins before the final design: a technical consultation with the city council or a municipal technician allows you to confirm the applicable procedure. With this information, finalize the architectural solution in accordance with regulations (alignments, aesthetics, setbacks) and avoid redesigns that delay the deadline. Next, ask your technical team to prepare a "requirement-proof" dossier: legible plans, surface area tables, clear regulatory justification, and consistent measurements. Finally, register the occupation of public roads if you will be placing scaffolding or containers there.
What to do if you are asked to correct something
A request for additional information is not a failure: it is an opportunity to clarify. Act quickly and decisively. Identify the cause (missing plan, surface discrepancy, omission of construction details), prepare the correction, and accompany it with an explanatory note. Avoid redoing the entire file if it is not necessary. Each correction usually adds between one and three weeks, so reducing their number is essential to shorten the total time frame for the building permit.
Frequent cases by type of action
Indoors, changing floors, tiling, false ceilings, private installations, and minor redistributions are usually processed by means of a communication or responsible declaration, and can begin almost immediately. When introducing aerothermal energy with an outdoor unit, facade extractor, smoke outlet, or equipment on the roof, the file may be transferred to a building permit. Outdoors, replacing windows while maintaining dimensions and color varies by municipality: some allow notification, others require a building permit. Enclosing a terrace or opening a new opening will always require a permit and, often, a technical project.
Costs and fees: how they impact deadlines
They don't speed things up on their own, but paying them well the first time around prevents suspensions. Calculate the rates based on the material execution budget and apply the waste management bond when applicable. Include these amounts in your financial forecast: it will help you decide when to register the building permit and when to sign supply contracts. If you use efficiency or accessibility bonuses, include the supporting documents from the outset.
Pre-registration checklist
Before uploading your file to the electronic registry, check five points: the type of procedure involved, consistency between plans and reports, fees paid, the need for additional reports, and the planned occupation of public roads. Also attach a summary of the scope and a milestone schedule; this will make it easier for the reviewer to understand and reduce questions. This small internal quality control check can often save weeks in the building permit process.