A turnkey house is one built under a single contract with a single company, which takes on the design, the licence paperwork and the construction work until it hands over the finished home for an agreed price and timescale. The landowner deals with a single point of contact instead of separately hiring an architect, a site execution director and a building contractor.
The formula simplifies coordination, but whoever commissions the home remains the developer (promotor) for the purposes of Ley 38/1999, de Ordenación de la Edificación (LOE, the Spanish Building Act). What the price covers depends on the scope written into the contract and the specification schedule (memoria de calidades).
What a turnkey house includes and what is usually left out
The term has no legal definition, so each company sets its own scope. Typically the price covers the design, the paperwork and the construction of the home, and leaves out whatever depends on the plot or the local council.
| Item | Usually included | Usually left out |
|---|---|---|
| Design and technical team | Basic and detailed design, construction management and health and safety coordination | Topographic and geotechnical surveys |
| Paperwork | Preparing and submitting the building licence application | Licence fee and construction tax (ICIO) |
| Construction | Foundations, structure, envelope, services and finishes as per the specification schedule | Extra foundation costs due to unforeseen ground conditions |
| Utilities | Internal installations within the home | Water, electricity, drainage and telecommunications connections |
| Plot | Earthworks required for the house | Land, boundary fencing, access, landscaping and swimming pool |
| Fit-out | Sanitaryware, taps and joinery listed in the specification | Kitchen, appliances and furniture |
No exclusion is improper as long as it is set out in writing. The problem arises when comparing offers with different scopes: the lowest figure may correspond to a home with no utility connections or external works. The overall cost is analysed in how much it costs to build a house on a plot.
Turnkey versus contracting separately
In traditional contracting the developer commissions the design from an architect, requests tenders from several contractors on the basis of that document, and hires the site supervision team (dirección facultativa) independently.
| Aspect | Turnkey | Contracting separately |
|---|---|---|
| Point of contact | One company is responsible for both design and construction | Architect, site execution director and contractor, under separate contracts |
| Oversight of the builder | The technical team usually belongs to the company or is hired by it | The site supervision team works for the developer |
| Claims for defects | The company is contractually liable for the whole | It must be established whether the cause lies in the design or in the execution |
| Design flexibility | Wide with a bespoke design, limited with catalogue models | Complete: the design is drawn up before choosing a contractor |
| Comparability of offers | Low: each company quotes for its own design and specification | High: all contractors price the same bill of quantities |
| Price and timescale | Known early, sometimes on the basis of a preliminary design | Known once the detailed design is complete |
What a fixed price means and under what conditions it holds
A fixed price is equivalent to the lump-sum contract (ajuste alzado) of Article 1593 of the Spanish Civil Code: a contractor who agrees a global figure on the basis of an agreed plan cannot ask for an increase even if wages or materials go up. They can do so when the owner authorises a change to the plan that involves more work. The figure depends on four conditions.
- Complete detailed design: a price given on a preliminary or basic design is an estimate. It is only fixed once there are quantities and construction details.
- Defined specification schedule: with specific brands, models or ranges. Expressions such as “top-quality” or “or similar” leave the choice to the builder.
- Client modifications: each change is priced and signed off before it is carried out, with its effect on price and timescale.
- Unforeseen ground conditions: the contract must state who bears the cost of more expensive foundations. With the geotechnical survey done before signing, that risk is built into the price.
A price revision clause linked to an index cancels out the protection against rises in material costs. VAT must be expressly stated as either included or excluded.
Clauses the contract must contain
Six clauses are the usual source of disputes between developer and company.
| Clause | What it should say | What it prevents |
|---|---|---|
| Scope | List of what is included and an express list of exclusions, with the design as an annex | Items invoiced separately because they were not mentioned |
| Specification schedule | Materials, brands or ranges and equipment, signed as an annex | Substitutions with lower-grade products |
| Payment schedule | Payments against verifiable milestones (foundations, structure, roof, finishes), not dates | Paying in advance for work not yet carried out |
| Timescale and penalties | Start linked to the licence, construction period and a penalty per day or week of delay | Delays with no financial consequence |
| Change management | Quote and written approval before carrying out each modification | Extras claimed at the end of the works |
| Guarantees | Retention until handover, guarantee periods, insurance and repair procedure | Defects with no swift route to a claim |
The LOE allows the one-year insurance on finishes to be replaced by a retention of 5% of the material execution cost of the works.
Site supervision, insurance and guarantees set by the LOE
The LOE distinguishes the builder from the site supervision team (dirección facultativa), made up of the construction director (director de obra) and the site execution director (director de la ejecución de la obra). These professionals check that what is built matches the design, approve the payment certificates and sign the certificate of completion.
The law does not prevent the same company that builds from providing them, but in that case whoever validates the work depends on whoever carries it out. It is advisable for the developer to hire or appoint the site supervision team, or for the contract to allow them to appoint their own technician with access to the site.
Liability for material damage has three periods, counted from the handover certificate (acta de recepción):
- Ten years for defects in foundations and structure that compromise the strength and stability of the building.
- Three years for defects in construction elements or installations that fail to meet habitability requirements.
- One year for workmanship defects in finishes, for which the builder is liable.
Ten-year structural insurance (seguro decenal), which backs the first period, is compulsory for residential buildings. The second additional provision of the LOE exempts individual self-builders of a single detached home for their own use. If the house is sold within ten years, the self-builder must, unless otherwise agreed, take out the insurance for the remaining period; they are only exempt if they can prove they have lived in the home and the buyer expressly releases them.
The exemption does not reduce the liability of the parties involved; it only removes the policy backing it. Waiving the insurance saves the premium in exchange for depending on the contractor’s solvency for ten years.
When a turnkey house makes sense and when it does not
Situations where it fits
- The developer has neither the time nor the experience to coordinate several parties.
- The overall cost needs to be known early, for example to apply for financing.
- The brief is conventional and allows for solutions the company has already built.
Situations where it fits less well
- A singular design or a complex plot, with a steep slope, irregular geometry or heritage protection.
- An interest in comparing several contractors on the same design.
- A decision still open on whether to buy or build a home, which must be settled before requesting offers.
Checklist before signing
- Commission the geotechnical and topographic surveys, and confirm the plot’s planning conditions with the local council.
- Require the detailed design, the specification schedule and the list of exclusions as signed annexes.
- Identify the construction director and the site execution director, and know who hires them.
- Check completed projects, client references and the company’s public liability insurance.
- Verify that payments are linked to milestones and that there is a retention until handover.
- Decide expressly whether to take out ten-year structural insurance.
A good many of the common mistakes when building a home stem from signing with the design still open.
What Cabana does in the construction of a detached home
Cabana is a Madrid architecture studio involved in detached home construction from plot analysis through to the end of the works. It draws up a bespoke design, prepares the licence documentation and manages the construction to check that it matches the design.
In summary
A turnkey house brings design, management and construction together in a single contract. Its scope is set by the contract and the specification schedule, and what is usually left out is the land, the preliminary surveys, municipal fees and taxes, utility connections, external works and fit-out.
A fixed price is only fixed with a complete detailed design and a defined specification, and it changes with client modifications and with unforeseen ground conditions the contract does not allocate. Before signing, it is advisable to secure a site supervision team answerable to the developer, milestone payments with a retention, and an informed decision on ten-year structural insurance.
Frequently Asked Questions
Does a turnkey house include the land?
Generally not. The client provides a plot already purchased or in the process of being purchased, and the company works on it. Some offers bundle land and home together, but in that case it is advisable to analyse the price and the planning conditions of the land separately.
Who applies for the building licence in a turnkey contract?
The company usually prepares and submits the documentation, but the LOE places the obligation to process and obtain licences on the developer, who is the one who pays the fee and the tax. The contract should clarify how a delay on the council’s part affects the delivery date.
Can a turnkey house be financed with a mortgage?
Yes, through a self-build mortgage, which the lender releases in stages as the work is certified. It is advisable for the contract’s payment schedule to match those drawdowns, whose terms are set by each bank.
What happens if the contractor goes bankrupt during the works?
The developer keeps what has been built on their plot, but must hire another company to finish, usually with extra cost and delay. The risk is limited by paying only for work carried out and requesting a bank guarantee if the contract provides for advance payments.
What documentation is handed over with the keys?
The handover certificate, the certificate of completion and the Building Book (Libro del Edificio), which brings together the design with its modifications, the list of parties involved and the use and maintenance instructions. With that documentation the first occupancy licence, in the form set by each municipality, and the new-build deed are processed.